November 26, 2013 4:22 am
Published by caladmin
Daniel O’Connell’s Sons served as the General Contractor for owner Liberty Utilities in their selective upgrading of two Liquid Natural... View Article
November 26, 2013 4:20 am
Published by caladmin
This aggressively paced project involved the performance of all Civil work for a new power substation as a subcontractor for... View Article
November 26, 2013 4:20 am
Published by caladmin
An extensive gas yard upgrade, this project consisted of Mechanical, Civil and Electrical work done for Spectra Energy in Burrillville,... View Article
November 26, 2013 4:19 am
Published by caladmin
Baileyville Compressed Natural Gas (CNG) Station was an EPC contract awarded to DOC which included the design and construction of... View Article
November 26, 2013 4:18 am
Published by caladmin
Phase III of this comprehensive upgrade included improvements to the solids management facilities at the Upper Blackstone WWTF, which services... View Article
November 26, 2013 4:17 am
Published by caladmin
Construction of a 20 million-gallon covered drinking water storage facility to provide higher and more stable water pressures to a... View Article
November 26, 2013 4:13 am
Published by caladmin
Replacement of the Lyman Street Bridge superstructure over the first level canal in Holyoke, MA. Client: MassDOT Designer: ... View Article
November 26, 2013 4:13 am
Published by caladmin
Rehabilitation adn cleaning of Primary and Secondary Clarifiers at the Deer Island Wastewater Treatment Plant serving the greater Boston area. ... View Article
November 26, 2013 4:11 am
Published by caladmin
As Design/Builder, Daniel O’Connell’s Sons collaborated with NEFCO (an O’Connell subsidiary) in the design, permitting, construction and operation of this... View Article
August 29, 2013 3:47 pm
Published by caladmin
Construction of a new Storrow Drive/Leverette Connector Bridge, connecting Boston’s Storrow Drive with Interstate-93. Part of the Central Artery project,... View Article