Summit Natural Gas (Schmidt Takeover)

DOC completed the installation of 34 10″ fitting replacement of varying bend degrees and angles, in a variety of challenging lane closure and traffic patterns. We also managed and supported five additional HDD sites, ranging between 712 FT to 2085 FT, and one 180 FT jack and bore railroad crossing. The project also included four station builds and nine main line valve installations. DOC was responsible for pigging, pressure testing, and drying 68 miles of installed pipeline measuring 6″, 8″, and 10″ mainline.

 